Full report
What GAO Found
The National Aeronautics and Space Administration's (NASA) 10 major spaceflight projects discussed in this report have not yet fully implemented earned value management (EVM). As a result, NASA is not taking full advantage of opportunities to use an important tool that could help reduce acquisition risk. GAO assessed the 10 projects against three fundamental EVM practices that, according to GAO's best practices cost guide, are necessary for maintaining a reliable EVM system. GAO found shortfalls in two of three fundamental practices. Specifically, we found that More than half of the projects did not use an EVM system that was fully certified as compliant with the industry EVM standard.
Only 4 of the 10 projects established formal surveillance reviews, which ensure that key data produced by the system was reliable. The remaining 6 projects provided evidence of monthly EVM data reviews; however, the rigor of both the formal and informal surveillance reviews is questionable given the numerous data anomalies GAO found.
GAO also found that 3 projects had reliable EVM data while 7 had only partially reliable data. For the EVM data to be considered reliable per best practices it must be complete and accurate with all data anomalies explained.
NASA EVM focal points, headquarters officials, project representatives, and program executives cited cultural and other challenges as impediments to the effective use of EVM at the agency. Traditionally, NASA's culture has focused on managing science and engineering challenges and not on monitoring cost and schedule data, like an effective EVM system produces. As a result, several representatives said this information traditionally has not been valued across the agency. This sentiment was also echoed in a NASA study of EVM implementation. Also cited as a challenge to the effective use of EVM was NASA's insufficient number of staff with the skills to analyze EVM data. Without a sufficient number of staff with such skills, NASA's ability to conduct a sound analysis of the EVM data is limited. However, NASA has not conducted an EVM skills gap analysis to determine the extent of its workforce needs.
NASA has undertaken several initiatives aimed at improving the agency's use of EVM. For example, NASA strengthened its spaceflight management policy to reflect the industry EVM standard and has developed the processes and tools for projects to meet these standards through its new EVM system. While these are positive steps, the revised policy contains only the minimum requirements for earned value management. For example, it lacks a requirement for rigorous surveillance of how projects are implementing EVM and also does not require use of the agency's newly developed EVM system to help meet the new requirements. NASA has attempted to address EVM shortcomings through policy changes over the years, but these efforts have failed to adequately address the cultural resistance to implementing EVM.
Why GAO Did This Study
NASA historically has experienced cost growth and schedule slippage in its portfolio of major projects and has taken actions to improve in this area, including adopting the use of EVM. EVM is a tool developed to help project managers monitor risks. GAO was asked to examine (1) the extent to which NASA is using EVM to manage its major space flight acquisitions, (2) the challenges that NASA has faced in implementing an effective EVM system, and (3) NASA's efforts to improve its use of EVM. To address these questions, GAO obtained contractor and project EVM data and used established formulas and tools to analyze the data and assess NASA's implementation of EVM on 10 major spaceflight projects; interviewed relevant NASA headquarters, center and mission directorate officials on their views on EVM; and reviewed prior reports on EVM and organizational transformations. GAO compared NASA policies and guidance on EVM to best practices contained in GAO's cost estimating best practices guide.
What GAO Recommends
Original post:
NASA: Earned Value Management Implementation across Major Spaceflight Projects Is Uneven (GAO)
- 2D Laser Profiling Scanner for Detecting Targets [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- NASA Energy Concept Could Harness the Power of Ocean Waves [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- Data Acquisition Modules [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- Dr. Scott Barthelmy, Research Scientist, Laboratory for High Energy Astrophysics, Goddard Space Flight Center, Greenbelt, MD [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- Laser Tracker Ensures Accurate Alignment of Ares I Components [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- Dual Cryogenic Capacitive Density Sensor [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- Advanced Technologies Will Help Hubble Yield More Remarkable Discoveries [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- Dr. Gerard Holzmann, Senior Research Scientist at the Laboratory for Reliable Software, NASA’s Jet Propulsion Laboratory [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- NASA Research Will Help Aircraft Avoid Ocean Storms and Turbulence [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- NASA Awards 2008 Software of the Year [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- Here Come The Tricorders - Update [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- China's View on Space [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- Milsat Coordination and Tracking Issues [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- Trash Talking and End Runs at NASA HQ [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- Ares 1-Y is Toast [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- Beyond Augustine [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- Analyzing LCROSS' Plume [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- Live Event: NASA-Sponsored Power Beaming Challenge [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- JSC Wants To Build a Replicator [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- USA: Looking For Ways To Hang On [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- Lunar Lander Challenge Prizes Awarded [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- Senate Votes To Restore NASA Budget Cuts [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- New FAA Regs for Commercial Reentry [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- TEDxNASA: An Invitation-Only NASA Meeting - Unless You Are Lucky [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- Close Call For Courtney Stadd [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- Space: A Waste? [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- Making NASA Cool [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- Engaging JSC’s Next Gen: A Leadership Analysis [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- Dumpster Diving for Rockets [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- TEDx NASA [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- Reflections On a Business Trip in Huntsville [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- Staying the Course [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- The Economics of Space [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- Ideas at Work [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- Blah Blah Blah - Why We Should Care About Social Media [Last Updated On: November 8th, 2009] [Originally Added On: November 8th, 2009]
- Will White House Speak Soon About NASA? [Last Updated On: December 12th, 2009] [Originally Added On: December 12th, 2009]
- Software Aids Design of Ares V Composite Shroud Structure [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- ASDX Series of silicon pressure sensors [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- Industry Update: Analysis & Simulation Software [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- Battery Will Provide Backup Power for Space Shuttles [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- NASA Employee Claims To Have Witnessed Hijacking Planning [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- Big Party in The Mojave Tonight [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- Looking at Boulders on the Moon [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- SpaceBook Featured by White House [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- New Ways to Use Constellation Stuff [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- LaRC internal Poll Update [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- Coalition for Space Exploration Does a (Much Needed) Reboot [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- Lunar Orbiter: Comparing Old and New Images [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- Boulder Trails On The Moon [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- Vote for John Grunsfeld - National Geographic Adventurer of the YeAR [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- Charlie Bolden at WIA/AIAA [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- Live Webcast From The Lunar Orbiter Image Recovery Project [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- Big Aerospace Warns of Job Cut Impact [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- The Boulders of Copernicus [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- shame on us [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- 2009 Space Elevator Games [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- Random Hacks of Kindness [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- TEDx NASA Tickets Available to the Public [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- It’s better in person [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- Leading Amidst the Disruptive Innovation Storm [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- Space: What’s NOT to Hope for? [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- Government in the Digital Age [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- SpaceUp – A Space Unconference [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- Starfleet Academy? [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- Crowdsourcing NASA [Last Updated On: December 13th, 2009] [Originally Added On: December 13th, 2009]
- Bringing Home The Bacon [Last Updated On: December 14th, 2009] [Originally Added On: December 14th, 2009]
- Anti-Space Mom with Pro-Space Kids [Last Updated On: December 14th, 2009] [Originally Added On: December 14th, 2009]
- How Quickly We Forget [Last Updated On: December 14th, 2009] [Originally Added On: December 14th, 2009]
- WISE Launch A Success [Last Updated On: December 14th, 2009] [Originally Added On: December 14th, 2009]
- Dynetics Buys Orion Propulsion [Last Updated On: December 15th, 2009] [Originally Added On: December 15th, 2009]
- New NASA Governance Structure Under Development [Last Updated On: December 16th, 2009] [Originally Added On: December 16th, 2009]
- Bolden Meets With Obama on Wednesday [Last Updated On: December 16th, 2009] [Originally Added On: December 16th, 2009]
- MSFC Procurement Doesn't Understand what "Open Source" Means [Last Updated On: December 16th, 2009] [Originally Added On: December 16th, 2009]
- Bolden Meets With Obama [Last Updated On: December 17th, 2009] [Originally Added On: December 17th, 2009]
- Parker Griffith AT MSFC Today [Last Updated On: December 18th, 2009] [Originally Added On: December 18th, 2009]
- Why Your NASA Computer May Not Work Properly [Last Updated On: December 18th, 2009] [Originally Added On: December 18th, 2009]
- Lakes and Fog on Titan [Last Updated On: December 18th, 2009] [Originally Added On: December 18th, 2009]
- Waterworld Found [Last Updated On: December 18th, 2009] [Originally Added On: December 18th, 2009]
- Pandora Could Exist [Last Updated On: December 18th, 2009] [Originally Added On: December 18th, 2009]
- Laurie Leshin Is The New ESMD Deputy AA [Last Updated On: December 18th, 2009] [Originally Added On: December 18th, 2009]