TYLER TxDOT is planning to conduct the following construction and maintenance work in the district during the week of Sep. 6, 2021. Work schedules are subject to change due to weather conditions, equipment failure, or other unforeseen issues. Slow down and pay attention in work zones.
----------------------------------------
Anderson County
Palestine Maintenance plans to continue ditch work on SH 294. Expect lane closures with flaggers and a pilot car managing traffic control.
Anderson County construction projects updates:
County Road Off-System Bridge Project
Limits: Various locations in Anderson County
Contractor: Stateline Construction, LLC
Cost: $1.5 million
Anticipated Completion Date: Completed
The contract consists of the construction of bridges, storm sewer, guardrail, base, pavement surfaces, and pavement markings.
US 79 Super 2 Project
Limits: From 0.5 mile northeast of Loop 256 to the Anderson/Cherokee County line
Contractor: Madden Contracting Company, LLC
Cost: $14.4 million
Anticipated Completion Date: Spring 2022
The contractor is scheduled to continue work on roadway elements. The speed limit has been reduced to 60 mph throughout the project limits. Motorists should use caution when traveling through the project and expect lane closures and delays. Project consists of widening for a Super 2, including sub-grade work, surface treatment, base and surface hot-mix asphalt, widening structures, bridge rail, metal beam guard fence, signage and permanent striping.
----------------------------------------
Cherokee County
Jacksonville Maintenance will be working on edge repairs at various locations throughout the area. Expect lane closures with flaggers managing traffic control.
Rusk Maintenance will continue base repair on FM 1857. Expect lane closures with flaggers managing traffic control.
Cherokee County construction projects updates:
FM 22 Safety Widening and Bridge Replacement Project
Limits: From CR 1512 west of Gallatin, east to SH 110
Contractor: Stateline Construction, LLC
Cost: $5.5 million
Anticipated Completion Date: Summer 2022
The contractor is scheduled to continue bridge construction at Sandy Creek. The roadway will be closed to traffic. Motorists should follow the marked detour route. The project will widen the existing roadway, replace three bridges and incorporate safety upgrades.
US 84 Widening
Limits: From 0.43 mi east of SH 110 in Rusk, northeast to the Rusk County line in Reklaw
Contractor: Madden Contracting Company, LLC
Cost: $7.9 million
Anticipated Completion Date: Summer 2022
The contractor is scheduled to continue right-of-way clearing and begin construction on driveway pipe and cross structure upgrades. Expect lane closures with delays. The project will widen and resurface the roadway, and add safety upgrades.
FM 235 Safety Widening
Limits: From SH 110 going east to FM 2274
Contractor: Madden Contracting Company, LLC
Cost: $3.5 million
Anticipated Completion Date: Fall 2021
The contractor is scheduled to continue placing signs, finish backfilling pavement edges and complete construction of driveways. Expect lane closures with a pilot car managing traffic. The project will widen the existing roadway and incorporate safety upgrades.
FM 241 Safety Widening
Limits: From US 69 going southeast to SH 21
Contractor: A. L. Helmcamp, Inc.
Cost: $5.5 million
Anticipated Completion Date: Completed
The project is widening the existing roadway and includes safety upgrades. The project is completed.
County Road Bridge Replacement Project
Limits: CR 2905 at Bowles Crk; CR 2614 at Beans Crk; CR 1504 at Turnpike Crk; CR 3203 at Mills Crk.
Contractor: Stateline Construction, LLC
Cost: $1.9 million
Anticipated Completion Date: Summer 2021
No work is scheduled on CR 3203 and CR 1504. Both roadways are open to traffic. Construction of the new bridges is ongoing on CR 2905 and CR 2614. Both roads are closed to through traffic. The project is replacing the existing bridges at each location with new structures.
SH 204 Super-2 Widening Project
Limits: From US 79 in Jacksonville southeast to SH 110
Contractor: Madden Contracting Company, LLC
Cost: $13.7 million
Anticipated Completion Date: Summer 2021
The contractor is scheduled to begin installing rumble strips, prefab pavement markings and removing excess silt from SW3P control measures. Lane closures will be in place. The project adds passing lanes and incorporates safety upgrades.
US 69 Sidewalks in Jacksonville
Limits: From Nacogdoches St. to Tena St. in Jacksonville
Contractor: Highway 19 Construction, LLC
Cost: $507,099.00
Anticipated Completion Date: Summer 2021
No work is scheduled. The project is constructing sidewalks along US 69 in Jacksonville.
US 79 Rehabilitation Project
Limits: From 0.16 mile east of SH 110 to the Mud Creek Relief Bridge
Contractor: Madden Contracting Company, LLC
Cost: $8.2 million
Anticipated Completion Date: Summer 2021
The contractor is scheduled to finish final surface striping. Lane closures will be in place, expect delays on this corridor when construction is in progress. The work zone speed limit is 60 mph. The project will rebuild the roadway pavement and upgrade bridge rails.
----------------------------------------
Gregg County
Longview Maintenance will be cleaning ditches on FM 1844. The crews will continue work on bridge channel maintenance on FM 2275 and FM 2204. Herbicide operations will also begin on various roadways. Expect lane closures with flaggers providing traffic control.
Gregg County construction projects updates:
Spur 63/McCann Road Bridge Project
Limits: From McCann Road, north to Glencrest Lane
Contractor: Leland Bradlee Construction
Anticipated Completion Date: November 2021
This project is part of the City of Longview Guthrie Creek Trail project. It will consist of building a bridge over Guthrie Creek to allow bicyclist and pedestrians to travel under Spur 63. The traffic will be reduced to two lanes, one northbound lane and one south bound lane to allow the contractor to build half of the bridge. Traffic will be switched later to allow completion of the bridge construction. Expect delays.
FM 2204, etc., Safety Improvement Project
Limits: US 259 Bypass to SH 322
Contractor: Stateline Construction
Cost: $3.8 million
Anticipated Completion Date: November 2021
This project consists of culverts, safety end treatments, drainage upgrades, new metal beam guard fence and driveway asphalt. Contractor will be working on drainage upgrades and driveways. There will be daytime lane closures. Expect delays.
FM 2206/Harrison Road
Limits: From Loop 281 to Fisher Rd.
Contractor: East Texas Bridge, Inc.
Cost: $15.1 million
Anticipated Completion Date: December 2021
This project consists of widening a two-lane road to four lanes with a center turn lane. This includes drainage structures, flexible base, curb and gutter, sidewalks, hot mix and pavement markings. Contractor will be extending culverts and constructing detours. There will be daytime lane closures. Expect delays.
FM 2206/Harrison Road
Limits: Fisher Rd. to SH 42
Contractor: East Texas Bridge, Inc.
Cost: $14.1 million
Anticipated Completion Date: May 2022
This project consists of widening a two-lane road to four lanes with a center turn lane. This includes drainage structures, new bridge, flexible base, hot mix and pavement markings. Contractor will be extending culverts and constructing detours. There will be daytime lane closures. Expect delays.
I-20/SH 31
Limits: Intersection with SH 31
Contractor: CorsairUS
Read more:
TxDOT Project Updates for the Week of Sep. 6, 2021 - Texas Department of Transportation