As the United States develops offshore wind capacity, the need for vessels to support the industry for installation and maintenance will rapidly expand. While it may seem perfectly logical for the industry to adopt the BIMCO WINDTIME form, the SUPPLYTIME 2005 form is more common and generally known to the U.S. service and supply-vessel industry. In any case, we wholly expect that there will be a good deal of modifications to any form or perhaps use of bespoke agreements as the work comes online. We review here the various forms available and look at particular terms and issues we expect to be the subject of specific negotiation and modification.
SUPPLYTIME: Then and Now
The SUPPLYTIME form was first developed in 1975 to meet the rising demand for specialty vessels to support offshore oil and gas exploration and production. This form and its progeny became the leading time-charter terms for offshore-support vessels, and its use has spread beyond the oil and gas industry to include cable and pipe laying, seismic work, anchor handling, surveying, ROV and dive support, and other offshore and near-shore construction work. While there is a 2017 version of the SUPPLYTIME, it hasnt been widely adopted in the United States, particularly since it came out after the substantial decrease in offshore oil and gas activity. (Interestingly, the drafting committee that developed the WINDTIME form differed from the SUPPLYTIME 2017 committee, and the difference is noticeable.) As for the U.S. offshore marine service and support industry, it appears that the SUPPLYTIME 2005 version remains prevalent at this time. (Obviously, any SUPPLYTIME form used with respect to the offshore wind industry would need to be logically amended to change oil and gas industry references to the appropriate wind-industry terms. For example, the term offshore unit in the SUPPLYTIME 2017 form is defined as any vessel, offshore installation, structure and/or mobile unit used in offshore exploration, construction, pipe-laying or repair, exploitation or production. There are also repeated reference to the defined term well.)
At the heart of the SUPPLYTIME form since the 1989 version came into play is a knock-for-knock indemnity provision, allocating liability regardless of fault with each party indemnifying the other for the injury or death of its personnel and for the loss of or damage to its propertywithout recourse. Initially, this was a difficult concept to accept in the United Statesthe idea that a party must indemnify another for a loss even though the loss was caused solely by the fault of the other party was a hard pill to swallow. However, in practice, the industry found it far more efficient for the parties to provide insurance for their own people and their own property and simply name the other party as an additional assured, rather than litigate every loss with each party claiming the other was at least partially to blame. The knock-for-knock indemnity concept is particularly efficient where a project involves a number of offshore contractors and all the parties agree to the same allocation of liability.
SUPPLYTIME vs. WINDTIME
The WINDTIME form, introduced in 2013, was primarily intended for offshore wind farm personnel transfer and support vessel services and was largely adopted from the SUPPPLYTIME 2005. Key differences from the SUPPLYTIME 2005 include:
It has been reported that the committee drafting the WINDTIME form initially considered, but quickly abandoned, the idea of including contract terms appropriate for installation vessels. We understand that industry practices for installation vessels were considered too varied and complex to reach consensus. Thus, the better option for installation vessels may be a SUPPLYTIME 2005 particularly modified to allocate liabilities and responsibilities, or a bespoke contract.
General Maritime and State Laws
As noted above, important differences between the SUPPLYTIME 2005 and the WINDTIME are the express inclusion of indemnity for gross negligence and the express exclusion of willful misconduct. This gets into an interesting issue under U.S. law in that the U.S. general maritime law varies from certain states laws as to whether a party may be indemnified for its own gross negligence. Under the U.S. general maritime law, a party may agree to indemnify another party for its own negligence, provided the terms are clear and unequivocal. With respect to state law, for example, under Virginia law, an agreement to indemnify a party for its own negligence is invalid. Under New York state law, the contract may validly require such indemnity, except for agreements concerning onshore building construction or maintenance.
While the SUPPLYTIME and WINDTIME forms each include an option to apply U.S. general maritime law, a court or arbitration panel may look to analogous state law if no entrenched federal maritime law exists. We believe U.S. maritime law is well entrenched with respect to indemnity for vessel operations such that state law should not be a factor, but we note that if the loss occurs onshore or implicates non-maritime activity or only involves a vessel tangentially, the knock-for knock indemnity may not be valid. Regardless of which form is used, the parties and their counsel should give careful consideration to the allocation of responsibility for claims.
Charterer Recourse and Consequential Damages
Another key difference between the WINDTIME and SUPPLYTIME 2005 forms is that the WINDTIME is more charterer-friendly with respect to delivery and cancellation. Under the SUPPLYTIME 2005, if owners fail to deliver the vessel by the cancellation date and charterers elect to cancel, charterers have little or no recourse against ownersgenerally similar to blue water time charters. This may be appropriate where other vessels are available to undertake the work, but could be problematic for specialty vessels where alternatives are limited. Under the WINDTIME, if it is clear that owners will be unable to deliver by the cancellation date, owners must notify charterers in writing, stating the date by which they will be able to deliver the vessel, and charterers have three days to cancel the charterparty. The WINDTIME form includes optional clauses concerning remedies for cancellation under these circumstances, ranging from: 1) drop hands (similar to the SUPPLYTIME form); to 2) reserving rights for claims; to 3) liquidated damages up to a capwith the default being the third option and the cap being 20 percent of total hire for the agreed period. We expect this may be a particularly fraught issue ripe for negotiation and potential dispute considering the time-sensitive nature of most wind farm projects.
The WINDTIME form includes a broader waiver of consequential damages than provided in the SUPPLYTIME 2005, but excludes the waivers application to several clauses, including bunker liability, knock-for knock indemnity, and pollution. As with the offshore oil and gas industry, limitation of consequential damages will be particularly important to owners in large complex offshore-construction projects related to wind-energy production, likely impacting substantial flow-down-contractual obligations. Regardless of the form in use, we highly recommend careful consideration of potential liability for consequential damages, and, if the WINDTIME form is used, note the default provisions.
Final Thoughts
Notwithstanding the foregoing, we expect that many of the parties involved in the fledgling U.S. offshore wind industry will come from the U.S.-based offshore oil and gas industry, but some may be experienced players from the more advanced European wind industry and more knowledgeable of its developed practices. Whether those practices and contractual terms will readily translate to work in U.S. waters and the application of U.S. law will need careful consideration.
At this time, it appears to us that a modified version of the SUPPLYTIME 2005 may be the most appropriate for offshore wind installation and maintenance operations. Regardless of the contract form, the parties will need to pay particular attention to the choice of law and the choice of forum and how those choices may impact the allocation of responsibility and liability between the parties. As with any contract, it is impossible to anticipate every circumstance that may arise, but we expect the experience gained from the offshore oil and gas industry may provide a good foundation for offshore wind operations and contractual terms.
The rest is here:
Offshore Wind Will Need Support Vessels What Form Are You Going to Use? - JD Supra
- BASF to Buy Stake in German Offshore Wind Farms From Vattenfall -- Update - MarketWatch - April 22nd, 2024 [April 22nd, 2024]
- Denmark Launches Massive Offshore Wind Auction | Offshore Wind - Offshore WIND - April 22nd, 2024 [April 22nd, 2024]
- rsted and OEG Renewables Form Offshore Wind Pact in US | Offshore Wind - Offshore WIND - April 22nd, 2024 [April 22nd, 2024]
- Vestas and Maersk team up for South Korean offshore wind - Recharge - April 22nd, 2024 [April 22nd, 2024]
- Denmark's offshore wind parks currently generate 2.7 gigawatts of electricity - The Mountaineer - April 22nd, 2024 [April 22nd, 2024]
- rsted Buys Sunrise Wind Stake from Eversource - Offshore WIND - April 22nd, 2024 [April 22nd, 2024]
- 'More non-turbine challenges' | GE hits back in New York round 3 offshore wind demise - Recharge - April 22nd, 2024 [April 22nd, 2024]
- 'Heart-breaking': Refugees once detained offshore by Australia warn the UK government not to push through its ... - The Albany Herald - April 22nd, 2024 [April 22nd, 2024]
- Hearing scheduled this week on bill to advance offshore wind - delawarebusinessnow.com - April 22nd, 2024 [April 22nd, 2024]
- Aker BP begins production from Hanz field offshore Norway - Offshore Technology - April 22nd, 2024 [April 22nd, 2024]
- Denmark launches its biggest offshore wind farm tender - The Caledonian-Record - April 22nd, 2024 [April 22nd, 2024]
- Vestas and Maersk to Build Offshore Wind Hub in South Korea | Offshore Wind - Offshore WIND - April 22nd, 2024 [April 22nd, 2024]
- U.S. Navy To Convert Oil Rigs Into Offshore Military Bases To Counter China In The Pacific - Marine Insight - April 22nd, 2024 [April 22nd, 2024]
- BASF seals deal to buy into gigascale Vattenfall offshore wind to power chemicals complex - Recharge - April 22nd, 2024 [April 22nd, 2024]
- First Moray West 14.7MW Offshore Wind Turbine Comes Up - Offshore Engineer - April 22nd, 2024 [April 22nd, 2024]
- NYSERDA concludes New York's third offshore wind solicitation without final awards - 4C Offshore - April 22nd, 2024 [April 22nd, 2024]
- Galp Energia says Namibia offshore field could contain 10B barrels of oil - Seeking Alpha - April 22nd, 2024 [April 22nd, 2024]
- Framework Agreement signed with rsted in the US - 4C Offshore - April 22nd, 2024 [April 22nd, 2024]
- A submerged concern: offshore wind cables - Martha's Vineyard Times - April 22nd, 2024 [April 22nd, 2024]
- Possible human smuggling operation thwarted offshore in South Florida - cw34.com - April 22nd, 2024 [April 22nd, 2024]
- Maersk sets sights on offshore wind logistics in South Korea - Splash247 - Splash 247 - April 22nd, 2024 [April 22nd, 2024]
- Brigantine, Ventnor respond to offshore wind suit dismissal - Press of Atlantic City - April 22nd, 2024 [April 22nd, 2024]
- Denmark launches 6GW offshore wind tender with an eye on production of green hydrogen and e-fuels - Hydrogen Insight - April 22nd, 2024 [April 22nd, 2024]
- Trump says he hates wind power at fundraiser with oil executives - The Washington Post - April 22nd, 2024 [April 22nd, 2024]
- Humboldt County Officials Headed to Massachusetts Next Week to Check Out Vineyard Offshore's Wind Farm - Lost Coast Outpost - April 22nd, 2024 [April 22nd, 2024]
- 3 More Offshore Wind Projects Bite the Dust - Heatmap - April 22nd, 2024 [April 22nd, 2024]
- Europe's First Commercial-Scale Floating Offshore Wind Farm Secures All Planning Approvals | Offshore Wind - Offshore WIND - April 22nd, 2024 [April 22nd, 2024]
- OEG Renewables lands US offshore wind contract with rsted - Energy Voice - April 22nd, 2024 [April 22nd, 2024]
- Vattenfall and BASF sign purchase agreement for 49 percent of Germany's Nordlicht offshore wind farms - Vattenfall - April 22nd, 2024 [April 22nd, 2024]
- House Republicans ask Gov. Moore to veto offshore wind financing bill - Ocean City Today - April 22nd, 2024 [April 22nd, 2024]
- Enterprise Products Partners Granted MARAD Port License For Biggest Offshore Oil Export Terminal In U.S. - Marine Insight - April 10th, 2024 [April 10th, 2024]
- RWE Wants to Expand Supply of Fiber Cables for Floating Offshore Wind - The Maritime Executive - April 10th, 2024 [April 10th, 2024]
- US unveils next steps in its 20242029 Gulf of Mexico oil & gas leasing program - Offshore Energy - April 10th, 2024 [April 10th, 2024]
- Romania adopts offshore wind energy law to get first megawatts by 2032 - Balkan Green Energy News - April 10th, 2024 [April 10th, 2024]
- Baltic Sea nations turn to Nato and EU to protect offshore infrastructure from Russian threats - Recharge - April 10th, 2024 [April 10th, 2024]
- Canadian Pension Fund to Consolidate Its Offshore Wind Holdings into UK-Based Reventus Power | Offshore Wind - Offshore WIND - April 10th, 2024 [April 10th, 2024]
- Australia urged to ensure its gas strategy features LNG opportunities - Offshore Energy - April 10th, 2024 [April 10th, 2024]
- Taiwan's offshore wind power moves forward. - 4C Offshore - April 10th, 2024 [April 10th, 2024]
- Siem Offshore lines up multi-year gig for 2016-built oil spill response vessel in Brazilian waters - Offshore Energy - April 10th, 2024 [April 10th, 2024]
- Poland's Largest Offshore Wind Project Readies for 2025 Auction | Offshore Wind - Offshore WIND - April 10th, 2024 [April 10th, 2024]
- New assignment for Wood in Trinidad and Tobago - Offshore Energy - April 10th, 2024 [April 10th, 2024]
- SalMar 'won't build offshore farms in Norway without ground rent tax' - FishFarmingExpert - April 10th, 2024 [April 10th, 2024]
- SLO County fishermen sue Coastal Commission, offshore wind companies. Weve got rights here - San Luis Obispo Tribune - April 10th, 2024 [April 10th, 2024]
- New floating offshore wind partnership committed to Celtic Sea - 4C Offshore - April 10th, 2024 [April 10th, 2024]
- Norwind Offshore's CSOV to Feature Seaonics Fully-Electric Crane - Offshore WIND - April 10th, 2024 [April 10th, 2024]
- Eversource's Offshore Wind Lessons Have Created A Buying Opportunity (NYSE:ES) - Seeking Alpha - April 10th, 2024 [April 10th, 2024]
- FERC approves collaboration between PJM, New Jersey to boost offshore wind - Daily Energy Insider - April 10th, 2024 [April 10th, 2024]
- April 10 Golden Knights vs Oilers NHL Offshore Betting Odds, Preview - The Latest Sports Betting News - OffshoreSportsbooks.com - April 10th, 2024 [April 10th, 2024]
- Arsenal vs Aston Villa EPL Offshore Odds, Preview, and Prediction - The Latest Sports Betting News - OffshoreSportsbooks.com - April 10th, 2024 [April 10th, 2024]
- O&Gs emissions reduction roadmap and the importance of refinery efficiency - Offshore Technology - April 10th, 2024 [April 10th, 2024]
- West Ham vs Fulham EPL Offshore Odds, Preview, and Prediction - The Latest Sports Betting News - OffshoreSportsbooks.com - April 10th, 2024 [April 10th, 2024]
- Liverpool vs Crystal Palace EPL Offshore Odds, Preview, and Prediction - The Latest Sports Betting News - OffshoreSportsbooks.com - April 10th, 2024 [April 10th, 2024]
- April 10 Astros vs Royals MLB Offshore Betting Odds, Preview - The Latest Sports Betting News - OffshoreSportsbooks.com - April 10th, 2024 [April 10th, 2024]
- RS helps propel offshore wind farm initiative in education sector - The Manufacturer - April 10th, 2024 [April 10th, 2024]
- Bournemouth vs Man United EPL Offshore Odds, Preview, and Prediction - The Latest Sports Betting News - OffshoreSportsbooks.com - April 10th, 2024 [April 10th, 2024]
- Grand National Offshore Odds, Preview, and Prediction (2024) - The Latest Sports Betting News - OffshoreSportsbooks.com - April 10th, 2024 [April 10th, 2024]
- Tyra, a State-of-the-Art Offshore Gas Hub in the North Sea - Total - April 10th, 2024 [April 10th, 2024]
- 50Hertz to start onshore works for Windanker offshore wind farm - Power Technology - April 10th, 2024 [April 10th, 2024]
- Fund manager Pelagic teams up with Borealis Maritime to expand offshore fleet - TradeWinds - April 10th, 2024 [April 10th, 2024]
- Another LNG carrier gets Silverstream's air lubrication tech at Seatrium - Offshore Energy - April 10th, 2024 [April 10th, 2024]
- VIDEO: EPS splashes USCG's first Heritage-class offshore patrol cutter - Naval Today - November 2nd, 2023 [November 2nd, 2023]
- N.J.s election focusing on abortion and offshore wind - WHYY - November 2nd, 2023 [November 2nd, 2023]
- Business Network for Offshore Wind changes name to Oceantic ... - WorkBoat - November 2nd, 2023 [November 2nd, 2023]
- Geotechnical Surveys Completed at Scottish 3.6 GW Floating ... - Offshore WIND - November 2nd, 2023 [November 2nd, 2023]
- Fitch downgrades Eversource outlook to 'negative' on uncertainty ... - Utility Dive - November 2nd, 2023 [November 2nd, 2023]
- Kongsberg & Solstad Offshore to Collaborate on Decarbonisation ... - The Maritime Executive - November 2nd, 2023 [November 2nd, 2023]
- Second BOEM in-person hearing on offshore wind generates ... - Ocean City Today - November 2nd, 2023 [November 2nd, 2023]
- NOV Earnings: Offshore Remains Central Performance Driver as ... - Morningstar - November 2nd, 2023 [November 2nd, 2023]
- Murphy eyes first oil in 2026 from offshore project in Southeast Asia - Offshore Energy - November 2nd, 2023 [November 2nd, 2023]
- CorPower Ocean's wave energy device weathers through two major ... - Offshore Energy - November 2nd, 2023 [November 2nd, 2023]
- Somerset offshore wind plant clears major hurdle - CommonWealth magazine - November 2nd, 2023 [November 2nd, 2023]
- In a 'world first,' autonomous giant drones are flying cargo to offshore ... - Electrek - November 2nd, 2023 [November 2nd, 2023]
- Port of VA Receives First Massive Offshore Wind Components - Chesapeake Bay Magazine - November 2nd, 2023 [November 2nd, 2023]
- HBA Future Energy to Build 532 MW Anma Offshore Substation - Offshore WIND - November 2nd, 2023 [November 2nd, 2023]
- PGE, rsted Gather Tier 1 Offshore Contractors for 1.5 GW Baltica 2 - Offshore WIND - November 2nd, 2023 [November 2nd, 2023]
- Philippine police unearth 'torture chamber' in sex den licensed as ... - The Straits Times - November 2nd, 2023 [November 2nd, 2023]
- CIP & Co Release Findings of Taranaki Offshore Wind Capability ... - Offshore WIND - November 2nd, 2023 [November 2nd, 2023]
- UK offshore wind stands up to Storm Ciaran - reNEWS - November 2nd, 2023 [November 2nd, 2023]
- Hatteras Offshore Open kicks off billfish series - The Coastland ... - The Coastland Times - May 18th, 2023 [May 18th, 2023]
- Anna Paulina Luna to feds: Study dangers of offshore wind turbines - Tampa Bay Times - May 18th, 2023 [May 18th, 2023]